November 8, 2021
Frederick Riggins and King Moses Riggins
538 B. S 18th St.
Newark, NJ 07103
RE: Unsafe Structure / Article 11.04
Old Minden Rd. District 9, Map 33, Parcel 127
To Whom it May Concern,
The Oak Hill City Council authorized the demolition of the structure located at Old Minden Rd., District 9, Map 33, Parcel 127, in Fayette County. City Council ordered the destruction under the city’s supervision and control because of failure of the property owner to comply with the order to demolish the structure given on August 9, 2021.
The demolition was completed on October 26, 2021. I have attached the demolition report the city manager submitted to City Council at their regular meeting on October 11, 2021. The cost associated with the Old Minden Rd. project is $7,800.59.
This order further advises you that at the next regular council meeting following the expiration of twenty days from the date of service of this order, Council will consider the adoption of a resolution laying the assessment. You shall be given an opportunity at the meeting to contest the legality of the assessment and the amount thereof. If Council adopts a resolution laying the assessment, a lien will be laid on the property. City Council meets the second Monday of each month at 6:30 p.m. in the Council Chambers at City Hall. Follow the link below to join the Zoom meeting if you are unable to attend in-person.
https://us02web.zoom.us/j/3044699541?pwd=Mk9raG14SmZmZlR3TmtuOEhKMEQ0Zz09 to join the Zoom Meeting. Meeting ID: 304 469 9541
Directions for Dial In by phone: Dial 301 715 8592 Meeting ID: 304 469 9541 Passcode: 421719
Respectfully,
Damita Johnson,
City Clerk/Treasurer
DEMOLITION REPORT
Demolition Ordered by City Council:
9/13/2021
Property Owner:
Frederick Riggins & King Moses Riggins
Structure Location:
Old Minden Rd.
Map 33 & Parcel 127
Bid Awarded to: Empire Salvage & Recycling, Inc.
PO Box 300 Bluefield. WV 24701
Notice to Proceed: 9/14/2021
Date of Inspection: 9/21/2021
Date of Asbestos Abatement: N/A
Date of Completion: 9/26/2021
Demolition Cost: $7,500.00
Administrative Cost –
Advertisement: $300.59
Total Cost: $7,800.59
Respectfully Submitted,
William C. Hannabass,
City Manager